The ____ for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any time during the project.
 a. total budgeted cost (TBC)
  b. cumulative budgeted cost (CBC)
  c. cumulative earned value (CEV)
  d. cumulative actual cost (CAC)
Read 54 times
1 Reply
Replies
Answer verified by a subject expert
dgonzalez228dgonzalez228
wrote...
Top Poster
Posts: 1198
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

banoshaher Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
Thank you, thank you, thank you!
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1166 People Browsing
 153 Signed Up Today
Related Images
  
 295
  
 385
  
 597
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 436