madhumeta madhumeta
wrote...
Posts: 704
Rep: 0 0
6 years ago
The ____ is the estimated cost to complete the activity in the crash time.
 a. opportunity cost
  b. path cost
  c. crash cost
  d. normal cost
Read 55 times
1 Reply
Replies
Answer verified by a subject expert
ashxeveashxeve
wrote...
Top Poster
Posts: 917
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

madhumeta Author
wrote...

6 years ago
Smart ... Thanks!
wrote...

Yesterday
Brilliant
wrote...

2 hours ago
This calls for a celebration Person Raising Both Hands in Celebration
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1353 People Browsing
 161 Signed Up Today
Related Images
  
 325
  
 121
  
 176
Your Opinion