Free slack is the amount of time a specific activity can be
 a. postponed without delaying the earliest start time of its immediately preceding activities.
  b. postponed without delaying the earliest start time of its immediately succeeding activities.
  c. accelerated without delaying the latest start time of its immediately succeeding activities.
  d. accelerated without delaying the latest finish time of its immediately preceding activities.
Read 43 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
b
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  452 People Browsing
Related Images
  
 330
  
 513
  
 903
Your Opinion
Who's your favorite biologist?
Votes: 608

Previous poll results: What's your favorite coffee beverage?