Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.
 a. day 6
  b. day 3
  c. day 4
  d. Cannot be calculated based upon information given.
Read 52 times
1 Reply
Replies
Answer verified by a subject expert
sky2walkersky2walker
wrote...
Top Poster
Posts: 957
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

plong717 Author
wrote...

6 years ago
this is exactly what I needed
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1030 People Browsing
Related Images
  
 155
  
 176
  
 309
Your Opinion