The ES and EF times are determined by calculating forward, that is, by
 a. adding all the times together for the project.
  b. working through the network diagram from the beginning of the project to the end of the project.
  c. calculating the optimistic and pessimistic times for the project.
  d. working through the network diagram from the end of the project to the beginning of the project.
Read 28 times
1 Reply
Replies
Answer verified by a subject expert
abenhadabenhad
wrote...
Top Poster
Posts: 859
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

zhamila Author
wrote...

6 years ago
Helped a lot
wrote...

Yesterday
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

2 hours ago
This calls for a celebration Person Raising Both Hands in Celebration
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1249 People Browsing
Related Images
  
 34
  
 249
  
 386
Your Opinion
What's your favorite funny biology word?
Votes: 328

Previous poll results: How often do you eat-out per week?