A project consisting of six activities is shown in the table. If the project manager decides to operate on a late start schedule, which of these days has the highest resource requirements?

Activity   Duration (days)   Activity Cost   Predecessor
K   10   140   
L   8   64   K, M
M   12   96   
N   6   120   M
P   14   168   L
Q   12   144   N

A) Day 21
B) Day 15
C) Day 24
D) Day 18
Textbook 
Project Management: Achieving Competitive Advantage

Project Management: Achieving Competitive Advantage


Edition: 4th
Author:
Read 373 times
3 Replies
Yuppp
Replies
Answer verified by a subject expert
flammableflammable
wrote...
Top Poster
Posts: 1729
8 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Louie928 Author
wrote...
8 years ago
Excellent, thx
Yuppp
wrote...
8 years ago
Good luck with the rest, Louie928
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1172 People Browsing
Related Images
  
 674
  
 215
  
 226
Your Opinion