A work center had planned outputs of 10, 15, 13, and 20 hours with actual outputs of 12, 14, 13, and 18 hours. What is the cumulative deviation in output?
A) 58
B) 0
C) 1
D) -1
E) Unable to determine with the given information
Textbook 
Operations Management

Operations Management


Edition: 10th
Authors:
Read 91 times
2 Replies
Replies
Answer verified by a subject expert
kadajikadaji
wrote...
Top Poster
Posts: 992
Rep: 9 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

sinnefoula Author
wrote...
6 years ago
Problem solved
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1392 People Browsing
Related Images
  
 598
  
 2850
  
 370
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 431