The jobs listed below need to be completed. Assume that it is now day 140. If the jobs are sequenced according to the shortest processing time rule, what is the average completion time?

Job   Processing Time (days)   Job due date (days)
A   20   180
B   30   200
C   10   175
D   16   230
E   18   210

A) 47.6 days
B) 94.0 days
C) 238.0 days
D) 2.5 days
E) 60.2 days
Textbook 
Operations Management

Operations Management


Edition: 10th
Authors:
Read 713 times
4 Replies
Replies
Answer verified by a subject expert
HplyEvrAftrHplyEvrAftr
wrote...
Top Poster
Posts: 1034
7 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Apatix Author
wrote...
7 years ago
I hope they pay you for the awesome work you do around here.

Thank you
Anonymous
wrote...
4 months ago
Help! The answer is missing an explanation...
wrote...
4 months ago
Done!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1874 People Browsing
Related Images
  
 4645
  
 360
  
 366
Your Opinion
Who's your favorite biologist?
Votes: 722