Vestor Ltd. has estimated a 90% cumulative average-time learning curve applies to labour time to manufacture its new product. The first unit took 18 hours. If Vestor's estimates are correct, how many hours will be used to manufacture 4 total units?
A) 14.58 hours
B) 64.80 hours
C) 72.00 hours
D) 64.01 hours
E) 58.32 hours
Textbook 
Cost Accounting: A Managerial Emphasis, Canadian Edition

Cost Accounting: A Managerial Emphasis, Canadian Edition


Edition: 7th
Authors:
Read 66 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
E
Explanation:  E) 18 * .9 * .9 = 14.58 average 14.58 * 4 = 58.32 hours
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1226 People Browsing
Related Images
  
 978
  
 202
  
 346
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 820