Vestor Ltd. has estimated a 90% cumulative average-time learning curve applies to labour time to manufacture its new product. The first unit took 18 hours. If Vestor's estimates are correct, how many hours will be used to manufacture 4 total units?
A) 14.58 hours
B) 64.80 hours
C) 72.00 hours
D) 64.01 hours
E) 58.32 hours
Textbook 
Cost Accounting: A Managerial Emphasis, Canadian Edition

Cost Accounting: A Managerial Emphasis, Canadian Edition


Edition: 7th
Authors:
Read 67 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
E
Explanation:  E) 18 * .9 * .9 = 14.58 average 14.58 * 4 = 58.32 hours
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  982 People Browsing
Related Images
  
 815
  
 337
  
 319
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 405