Given the network shown in Figure 11-1 and the following information, what is the variance of the critical path?

 Activity   Expected time   Variance
A   3   2
B   5   3
C   6   3
D   4   1
E   5   1
F   4   2
G   6   2
H   7   2

A) 16
B) 7
C) 9
D) 8
E) None of the above
Textbook 
Quantitative Analysis for Management

Quantitative Analysis for Management


Edition: 12th
Authors:
Read 35 times
2 Replies

Related Topics

Replies
wrote...
6 years ago
C
assignment009 Author
wrote...
6 years ago
thank uuuuuu
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  968 People Browsing
Related Images
  
 993
  
 317
  
 485
Your Opinion
Who will win the 2024 president election?
Votes: 7
Closes: November 4