For a project, the TBC = 200,000 . the CEV = 120,000 . the CAC = 100,000 . Which of the following statements is true?
 a. The project has a negative cost variance and corrective action is needed.
  b. The FCAC is greater than the budget and the project scope should be adjusted.
  c. The project is progressing well and should be continued.
  d. The CPI is less than 1.0.
Read 25 times
1 Reply
Replies
Answer verified by a subject expert
casssmcasssm
wrote...
Top Poster
Posts: 955
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

ovx1267 Author
wrote...

6 years ago
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

Yesterday
This site is awesome
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1133 People Browsing
Related Images
  
 214
  
 305
  
 447
Your Opinion
Who will win the 2024 president election?
Votes: 10
Closes: November 4