× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
6
y
2
m
2
m
2
u
2
m
2
B
2
M
2
e
2
k
2
N
2
y
2
New Topic  
ovx1267 ovx1267
wrote...
Posts: 663
Rep: 0 0
6 years ago
For a project, the TBC = 200,000 . the CEV = 120,000 . the CAC = 100,000 . Which of the following statements is true?
 a. The project has a negative cost variance and corrective action is needed.
  b. The FCAC is greater than the budget and the project scope should be adjusted.
  c. The project is progressing well and should be continued.
  d. The CPI is less than 1.0.
Read 33 times
1 Reply
Replies
Answer verified by a subject expert
casssmcasssm
wrote...
Top Poster
Posts: 955
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

ovx1267 Author
wrote...

6 years ago
You make an excellent tutor!
wrote...

Yesterday
Thank you, thank you, thank you!
wrote...

2 hours ago
Thanks for your help!!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  600 People Browsing
Related Images
  
 222
  
 332
  
 478
Your Opinion
What's your favorite math subject?
Votes: 559