For a project, the TBC = 200,000 . the CEV = 120,000 . the CAC = 100,000 . Which of the following statements is true?
 a. The project has a negative cost variance and corrective action is needed.
  b. The FCAC is greater than the budget and the project scope should be adjusted.
  c. The project is progressing well and should be continued.
  d. The CPI is less than 1.0.
Read 26 times
1 Reply
Replies
Answer verified by a subject expert
casssmcasssm
wrote...
Top Poster
Posts: 955
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

ovx1267 Author
wrote...

6 years ago
Brilliant
wrote...

Yesterday
Correct Slight Smile TY
wrote...

2 hours ago
Thank you, thank you, thank you!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1022 People Browsing
Related Images
  
 305
  
 447
  
 565
Your Opinion
Who will win the 2024 president election?
Votes: 10
Closes: November 4