cd627 cd627
wrote...
Posts: 698
Rep: 0 0
6 years ago
The earned value is
 a. the budgeted cost of the work scheduled.
  b. the sum of the actual costs of the project.
  c. difference between what was planned and the actual costs.
  d. the budgeted costs of the work actually performed.
Read 39 times
1 Reply
Replies
Answer verified by a subject expert
PercymatePercymate
wrote...
Top Poster
Posts: 1205
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

cd627 Author
wrote...

6 years ago
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

Yesterday
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1467 People Browsing
Related Images
  
 303
  
 377
  
 1527
Your Opinion
How often do you eat-out per week?
Votes: 81