The windmills of Mykonos were lovely, so Lisa contracted with an architectural firm to build one in the west pasture. Once the windmill had been built and was operational, the project team looked back at how they had managed to stay on schedule and what budget variances existed along the way. The windmill was pumping as promised, an honest two gallons per minute just as they had design it. Closeout documentation of this type is considered:
A) Historical records.
B) Hierarchy reporting.
C) Post-project analysis.
D) Financial closeout.
Textbook 
Project Management: Achieving Competitive Advantage

Project Management: Achieving Competitive Advantage


Edition: 4th
Author:
Read 652 times
3 Replies
Yuppp
Replies
Answer verified by a subject expert
flammableflammable
wrote...
Top Poster
Posts: 1729
8 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Louie928 Author
wrote...
8 years ago
Thank you again
Yuppp
wrote...
8 years ago
Thanks for the update! Happy Holidays
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  541 People Browsing
Related Images
  
 368
  
 751
  
 5951
Your Opinion
Who's your favorite biologist?
Votes: 608