A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. What is the probability that the project can be completed between days 108 and 120?
A) 0.9773
B) 0.4773
C) 0.1058
D) 0.0227
E) -2.00
Textbook 
Operations Management

Operations Management


Edition: 10th
Authors:
Read 85 times
1 Reply
Replies
Answer verified by a subject expert
AlmeyricAlmeyric
wrote...
Top Poster
Posts: 929
6 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Apatix Author
wrote...

6 years ago
Helped a lot
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Thanks for your help!!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  594 People Browsing
Related Images
  
 1091
  
 3628
  
 253
Your Opinion
Who's your favorite biologist?
Votes: 587

Previous poll results: How often do you eat-out per week?