In CCPM, a finite amount of time that can be added to a sequence of activities to non-critical tasks best describes
 
  A) negative float.
  B) safety float.
  C) relaxed capacity.
  D) feeding buffers.
Read 33 times
1 Reply
Replies
Answer verified by a subject expert
SolarhavaSolarhava
wrote...
Top Poster
Posts: 875
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

MADUBUCA76 Author
wrote...

6 years ago
Thank you, thank you, thank you!
wrote...

Yesterday
Good timing, thanks!
wrote...

2 hours ago
This site is awesome
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1096 People Browsing
Related Images
  
 1075
  
 54
  
 208
Your Opinion
How often do you eat-out per week?
Votes: 80

Previous poll results: Who's your favorite biologist?