Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.
 
  Activity Normal Time Normal Cost Crash Time Crash Cost
  One 8 days 6,000 6 days 6,800
  Two 10 days 4,000 9 days 5,000
 
  A) One; 400
  B) One; 6,800
  C) Two; 1,000
  D) Two; 5,000
  E) One or Two should be crashed; 1,400
Read 65 times
1 Reply
Replies
Answer verified by a subject expert
garyrangel12garyrangel12
wrote...
Top Poster
Posts: 926
Rep: 2 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

nramos08 Author
wrote...

6 years ago
Thank you, thank you, thank you!
wrote...

Yesterday
You make an excellent tutor!
wrote...

2 hours ago
Just got PERFECT on my quiz
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1235 People Browsing
Related Images
  
 998
  
 264
  
 485
Your Opinion
Which of the following is the best resource to supplement your studies:
Votes: 365

Previous poll results: Who's your favorite biologist?