Describe how crashing and fast tracking can be used to compress a project schedule. What limitations could there be with each of these methods?
Read 21 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
Key concepts to be covered in the response could include, but are not limited to:

Crashing: When crashing a project schedule, certain activities are performed at a faster-than-normal pace. This could require additional expenses such as overtime pay, more expensive machinery, etc. Crashing almost always costs more money in order to speed up the schedule.

Fast Tracking: In fast tracking, activities that are normally performed in a series (one after another) are performed at the same time. This speeds things up but can add risk.
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1010 People Browsing
Related Images
  
 169
  
 469
  
 108
Your Opinion
What's your favorite math subject?
Votes: 314