Project managers must often face the challenge of compressing the project schedule. All of the following actions can be taken to reduce the duration of the critical path EXCEPT:
 a. Reduce the project scope and /or quality.
  b. Overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
  c. Use the float in critical path activities
  d. Partially overlap sequential activities by using time leads.
Read 41 times
1 Reply
Replies
Answer verified by a subject expert
rcollins105rcollins105
wrote...
Top Poster
Posts: 914
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Inspectum Author
wrote...

6 years ago
Helped a lot
wrote...

Yesterday
This helped my grade so much Perfect
wrote...

2 hours ago
Thanks for your help!!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1304 People Browsing
Related Images
  
 282
  
 721
  
 880
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 352