All of the following problems contribute to difficulty in estimating activity durations accurately EXCEPT:
 a. merging - multiple predecessors
  b. omissions - leaving out key activities
  c. general uncertainty in the estimate
  d. poor vendor selection
Read 46 times
1 Reply
Replies
Answer verified by a subject expert
drawnbluddrawnblud
wrote...
Top Poster
Posts: 957
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Altysha Author
wrote...

6 years ago
Smart ... Thanks!
wrote...

Yesterday
Thanks
wrote...

2 hours ago
This site is awesome
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  775 People Browsing
Related Images
  
 268
  
 159
  
 518
Your Opinion
Who's your favorite biologist?
Votes: 587