× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
New Topic  
riz riz
wrote...
Posts: 694
Rep: 0 0
6 years ago
Which of the following statements concerning work packages is NOT correct?
 a. Work packages are the basis for subsequent project planning activities.
  b. Work packages are the basis for subsequent project control activities.
  c. Work packages are activity elements with detailed descriptions of tasks and dependencies
  d. Work packages are the elements at the lowest level of the WBS.
Read 116 times
1 Reply
Replies
Answer verified by a subject expert
abenhadabenhad
wrote...
Top Poster
Posts: 859
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

riz Author
wrote...

6 years ago
Correct Slight Smile TY
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1218 People Browsing
Related Images
  
 600
  
 379
  
 368
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 431