Which of the following statements concerning work packages is NOT correct?
 a. Work packages are the basis for subsequent project planning activities.
  b. Work packages are the basis for subsequent project control activities.
  c. Work packages are activity elements with detailed descriptions of tasks and dependencies
  d. Work packages are the elements at the lowest level of the WBS.
Read 152 times
1 Reply
Replies
Answer verified by a subject expert
abenhadabenhad
wrote...
Top Poster
Posts: 859
Rep: 3 0
7 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

riz Author
wrote...

7 years ago
You make an excellent tutor!
wrote...

Yesterday
This helped my grade so much Perfect
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  556 People Browsing
Related Images
  
 849
  
 494
  
 417
Your Opinion