New Topic  
macgeek312 macgeek312
wrote...
Posts: 663
Rep: 0 0
6 years ago
If the lead time is 1 week, the review period 4 weeks, the average demand 100 units per week and
  the safety stock is 50 units, the target level will be:
 
  A) 550 units. B) 300 units. C) 250 units. D) 150 units. E) 200 units.
Read 65 times
1 Reply
Replies
Answer verified by a subject expert
Ha d.Ha d.
wrote...
Top Poster
Posts: 876
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

macgeek312 Author
wrote...

6 years ago
Correct Slight Smile TY
wrote...

Yesterday
You make an excellent tutor!
wrote...

2 hours ago
Just got PERFECT on my quiz
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1181 People Browsing
 107 Signed Up Today
Related Images
  
 257
  
 836
  
 342
Your Opinion