A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule.
 
  The increase in project direct costs related to crashing activities would be 40,000. Also, project indirect costs are 15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?
  A) less than or equal to 5,000
  B) greater than 5000 but less than or equal to 10,000
  C) greater than 10,000 but less than or equal to 15,000
  D) greater than 15,000
Read 72 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
A
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1253 People Browsing
Related Images
  
 1520
  
 316
  
 301
Your Opinion
Who's your favorite biologist?
Votes: 586