The Northern Manufacturing Company is producing products A and B, using the same machine called MASAC27A. Demand forecasts for next year and other production-related information are provided in the following table.
 
  Product A Product B
  Demand forecast (units/yr) 4,000 12,000
  Batch size (units/batch) 80 150
  Processing time (hr/unit) 2.5 2.0
  Setup time (hr/batch) 16 12
 
  The company works 250 days per year and operates 2 shifts each day, each shift covering 8 hours. If 25 percent of capacity cushion is maintained throughout the year, how many machines (MASAC27A) does the company need next year to meet the demand? (Round your answer up to the next whole machine.)
  A) fewer than 11 machines
  B) 11 machines
  C) 12 machines
  D) more than 12 machines
Read 27 times
1 Reply
Replies
Answer verified by a subject expert
cvallierecvalliere
wrote...
Top Poster
Posts: 940
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Cynh972 Author
wrote...

6 years ago
Brilliant
wrote...

Yesterday
Correct Slight Smile TY
wrote...

2 hours ago
Good timing, thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1236 People Browsing
 124 Signed Up Today
Related Images
  
 1859
  
 305
  
 356
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 741