Consider the system composed of four processes linked by a conveyor belt. There is no storage between these processes pictured below and market demand of 40 units per hour drives the conveyor belt.
 
  Assume that no defective units are made. Which statement is best?
 
  A) The average time a unit spends in Process 1 is 2 and a half minutes.
  B) The average time a unit spends in Process 2 is 5 minutes.
  C) The flow time for a unit through the entire process is 33 minutes.
  D) The flow rate through the entire process is 160 units per hour.
Read 35 times
2 Replies
Replies
Answer verified by a subject expert
ashxeveashxeve
wrote...
Top Poster
Posts: 917
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

hmorris21 Author
wrote...
6 years ago
Great answer
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  777 People Browsing
Related Images
  
 185
  
 367
  
 458
Your Opinion
Who's your favorite biologist?
Votes: 587

Previous poll results: What's your favorite coffee beverage?