The heir to the throne was due 56 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery.
 
  The seven activities, their normal and expedited times (in days) and costs appear in the table. What is the minimum cost to ensure that this project is completed in 56 days? Which activities should be reduced and by how many days?
 
  Activity Normal time Crash time Normal Cost Crash Cost Predecessor
  A 5 3 500 1100
  B 18 15 900 2300 A
  C 12 9 2500 3000 A
  D 9 7 500 650 B
  E 15 12 3000 5000 B
  F 12 10 4000 5000 C, D
  G 20 15 3600 4800 E, F
Read 51 times
1 Reply
Replies
Answer verified by a subject expert
drawnbluddrawnblud
wrote...
Top Poster
Posts: 957
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

BoyzGonWild Author
wrote...

6 years ago
Brilliant
wrote...

Yesterday
Thanks for your help!!
wrote...

2 hours ago
Thank you, thank you, thank you!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  380 People Browsing
 107 Signed Up Today
Related Images
  
 2549
  
 119
  
 644
Your Opinion
Which is the best fuel for late night cramming?
Votes: 231