Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.
 
  A) 26
  B) 25
  C) 24
  D) 23
Read 131 times
1 Reply
Replies
Answer verified by a subject expert
babyfacelovebabyfacelove
wrote...
Top Poster
Posts: 903
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Micky5490! Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
dri
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Correct Slight Smile TY
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1228 People Browsing
Related Images
  
 297
  
 784
  
 353
Your Opinion
What's your favorite coffee beverage?
Votes: 303