Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.
 
  A) 8
  B) 13
  C) 14
  D) 21
Read 91 times
2 Replies

Related Topics

Replies
su
wrote...
6 years ago
C
Micky5490! Author
wrote...
6 years ago
Thank you so much