Create a resource loading table and perform resource leveling on the project composed of the activities in this table. Activities listed in the table are measured in the number of eight-hour days. The maximum amount of time used per day is 16 hours.
 
  Activity Time Predecessor
  A 6 --
  B 1 --
  C 2 A, B
  D 4 --
  E 1 C, D
  F 1 E
  G 6 E
  H 4 F
  J 4 F
  K 3 G, H
  L 5 J, K
  M 3 L
Read 87 times
1 Reply
Replies
Answer verified by a subject expert
lmslinkardlmslinkard
wrote...
Top Poster
Posts: 886
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Heskeksndfb Author
wrote...

6 years ago
Correct Slight Smile TY
wrote...

Yesterday
Good timing, thanks!
wrote...

2 hours ago
You make an excellent tutor!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1322 People Browsing
Related Images
  
 206
  
 235
  
 309
Your Opinion