A project is represented by the activity durations (in days, estimated at 90 likelihood of completion) and precedence requirements shown in the table.
 
  What is the length of a feeder buffer if this project is managed using critical chain methodology?
 
  Activity Predecessor Length Activity Predecessor Length
  A -- 18 E C, D 13
  B -- 16 F C 9
  C A 22 G E, F 15
  D B 14
  A) 3.5 days
  B) 2.5 days
  C) 1.5 days
  D) 0.5 days
Read 60 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
B