A project is represented by the activity durations (estimated at 90 likelihood of completion) and precedence requirements shown in the table.
 
  What is the length of the project buffer if this project is managed using critical chain methodology?
 
  Activity Predecessor Length Activity Predecessor Length
  A -- 20 D B 16
  B A 20 E C 8
  C A 10 F D, E 8
  A) 4.5
  B) 11.5
  C) 20.5
  D) 16
Read 86 times
1 Reply
Replies
Answer verified by a subject expert
shahanasshahanas
wrote...
Top Poster
Posts: 901
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

madhumeta Author
wrote...

6 years ago
This helped my grade so much Perfect
wrote...

Yesterday
Thanks
wrote...

2 hours ago
This calls for a celebration Person Raising Both Hands in Celebration
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1252 People Browsing
Related Images
  
 282
  
 700
  
 354
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 741