A project consists of four activities with information as shown in the table. What is the overall variance of the project's duration?
 
  Activity Predecessor Length Standard Deviation
  A -- 10 2
  B A 12 3
  C A 16 2
  D B, C 14 3
 
  A) 13
  B) 17
  C) 26
  D) 35
Read 29 times
1 Reply
Replies
Answer verified by a subject expert
unique101unique101
wrote...
Top Poster
Posts: 917
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

asourdillard Author
wrote...

6 years ago
Thanks
wrote...

Yesterday
Helped a lot
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  678 People Browsing
Related Images
  
 195
  
 244
  
 331
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 379