A project consists of four activities with information as shown in the table. What is the overall standard deviation of the project?
 
  Activity Predecessor Length Variance
  A -- 10 4
  B A 12 3
  C B 16 5
  D C 14 6
 
  A) 24
  B) 18
  C) 8.41
  D) 4.24
Read 43 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
D