Use the information in the table regarding this seven-month project to calculate the SPI in terms of dollars and compare it with the SPI calculated in terms of time. Perform both calculations for months 1 through 6.
 
  Then use the SPI(t) to provide the Estimate at Completion for Time (EACt).
 
   Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7
  PV () 125 275 500 875 1,485 2,325 2,670
  EV () 150 320 510 850 1425 2280 0
Read 37 times
1 Reply
Replies
Answer verified by a subject expert
npalmierinpalmieri
wrote...
Top Poster
Posts: 886
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Star4567980 Author
wrote...

6 years ago
Good timing, thanks!
wrote...

Yesterday
Smart ... Thanks!
wrote...

2 hours ago
This helped my grade so much Perfect
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  995 People Browsing
Related Images
  
 204
  
 103
  
 338
Your Opinion
Which of the following is the best resource to supplement your studies:
Votes: 292