If an assignment problem consists of 6 workers and 7 projects:
 
  A) one worker will not get a project assignment.
  B) one worker will be assigned two projects.
  C) each worker will contribute work toward the seventh project.
  D) one project will not get a worker assigned.
  E) The problem cannot be solved by assignment method.
Read 30 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
D