An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. What is its expected activity time?
 
  A) 2.00
  B) 2.33
  C) 2.67
  D) 4.67
  E) 14.00
Read 32 times
1 Reply
Replies
Answer verified by a subject expert
susu
wrote...
Top Poster
Posts: 910
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

asourdillard Author
wrote...

6 years ago
This site is awesome
wrote...

Yesterday
Brilliant
wrote...

2 hours ago
Correct Slight Smile TY
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  907 People Browsing
Related Images
  
 1089
  
 55
  
 31
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 820

Previous poll results: Where do you get your textbooks?