sinnefoula sinnefoula
wrote...
Posts: 1533
Rep: 1 0
7 years ago
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 8. What is its expected activity time and variance?
A) 3.67; 6
B) 3.67; 1
C) 4.33; 1
D) 4.33; 6
E) none of the above
Textbook 
Operations Management

Operations Management


Edition: 10th
Authors:
Read 73 times
2 Replies
Replies
Answer verified by a subject expert
HplyEvrAftrHplyEvrAftr
wrote...
Top Poster
Posts: 1033
7 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

sinnefoula Author
wrote...
6 years ago
Problem solved