Ejaylcuk Ejaylcuk
wrote...
Posts: 652
Rep: 0 0
6 years ago
_____ is the sequence of activities that takes the longest time and defines the total project completion time.
 a. Project Evaluation and Review Technique
  b. The critical path
  c. The crash time
  d. Project nodes network
Read 42 times
1 Reply
Replies
Answer verified by a subject expert
Studyboy45Studyboy45
wrote...
Top Poster
Posts: 933
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Ejaylcuk Author
wrote...

6 years ago
Thank you, thank you, thank you!
wrote...

Yesterday
Good timing, thanks!
wrote...

2 hours ago
Correct Slight Smile TY
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1025 People Browsing
Related Images
  
 267
  
 790
  
 630
Your Opinion
Which of the following is the best resource to supplement your studies:
Votes: 292