In Microsoft Project if task B need to begin two days after task A started, you would use a task dependency of _______.
 a. FS + 2 days
  b. SS + 2 days
  c. FS - 2 days
 d. SS - 2 days
Read 83 times
1 Reply
Replies
Answer verified by a subject expert
lmslinkardlmslinkard
wrote...
Top Poster
Posts: 886
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Kao Author
wrote...

6 years ago
This helped my grade so much Perfect
wrote...

Yesterday
You make an excellent tutor!
wrote...

2 hours ago
Thank you, thank you, thank you!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  991 People Browsing
Related Images
  
 330
  
 1541
  
 603