The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. Task A takes nine days to be completed instead of seven days. How much slack does the project have now that Task A is finished?
 a. Negative 5 days slack.
  b. Positive 5 days slack.
  c. Positive 16 days slack.
  d. Positive 3 days slack.
Read 63 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
d
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  987 People Browsing
Related Images
  
 1334
  
 150
  
 913
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 820