× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
New Topic  
Kao Kao
wrote...
Posts: 634
Rep: 0 0
6 years ago
In Microsoft Project if task B need to begin two days after task A started, you would use a task dependency of _______.
 a. FS + 2 days
  b. SS + 2 days
  c. FS - 2 days
 d. SS - 2 days
Read 93 times
1 Reply
Replies
Answer verified by a subject expert
lmslinkardlmslinkard
wrote...
Top Poster
Posts: 886
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Kao Author
wrote...

6 years ago
Good timing, thanks!
wrote...

Yesterday
Helped a lot
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  911 People Browsing
Related Images
  
 354
  
 2534
  
 591
Your Opinion
Where do you get your textbooks?
Votes: 447