In Microsoft Project if task B need to begin two days after task A started, you would use a task dependency of _______.
 a. FS + 2 days
  b. SS + 2 days
  c. FS - 2 days
 d. SS - 2 days
Read 80 times
1 Reply
Replies
Answer verified by a subject expert