Changes to a project will still occur, even with good plans. The project manager
 a. needs to be sure that team members casually agree to changes that may require additional person-hours.
  b. should estimate the effects on the project cost and schedule rather than having appropriate personnel estimate the effects of the change.
  c. controls the communication about the change and limits who knows a change has occurred.
  d. has project team members and the customer participate up front in the decision to change the project.
Read 40 times
1 Reply
Replies
Answer verified by a subject expert
shahanasshahanas
wrote...
Top Poster
Posts: 901
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

MADUBUCA76 Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

2 hours ago
Correct Slight Smile TY
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1274 People Browsing
Related Images
  
 137
  
 229
  
 291
Your Opinion
Which of the following is the best resource to supplement your studies:
Votes: 292