Risks on the critical path should be
 a. given lower priority than those activities with positive total slack.
  b. given equal priority than those activities with positive total slack.
  c. given higher priority than those activities with positive total slack.
  d. given higher priority than those activities with no total slack.
Read 38 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
c