Free slack of an activity is
 a. the slack on activities that do not have any costs associated with them.
  b. can be calculated on every activity with a serial relationship to its successors.
  c. the amount of time an activity can be postponed and not delay the start of its immediately succeeding activities.
  d. is always a negative value.
Read 68 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
c