If the total slack for a project is 4 days, this means
 a. the activities on the path can be delayed a total of four days and the project still could be completed on time.
  b. the activities on the path must be accelerated by four days for the project to be completed on time.
  c. all the activities must be accelerated by four days for the project to be completed on time.
  d. all the activities can be delayed by four days and the project still be completed on time.
Read 52 times
1 Reply
Replies
Answer verified by a subject expert
vulshafer15vulshafer15
wrote...
Top Poster
Posts: 889
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

abbiedigings Author
wrote...

6 years ago
Thanks
wrote...

Yesterday
This helped my grade so much Perfect
wrote...

2 hours ago
This site is awesome
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1379 People Browsing
Related Images
  
 1013
  
 856
  
 1248
Your Opinion