The ____ is the estimated cost to complete the activity in the crash time.
 a. opportunity cost
  b. path cost
  c. crash cost
  d. normal cost
Read 52 times
1 Reply
Replies
Answer verified by a subject expert
ashxeveashxeve
wrote...
Top Poster
Posts: 917
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

madhumeta Author
wrote...

6 years ago
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Correct Slight Smile TY
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1218 People Browsing
Related Images
  
 1089
  
 560
  
 48