If ____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion of the project by its required completion time.
 a. total time
  b. free time
  c. total slack
  d. cumulative slack
Read 42 times
1 Reply
Replies
Answer verified by a subject expert
grfrfvfbvrgrfrfvfbvr
wrote...
Top Poster
Posts: 916
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

asourdillard Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
Good timing, thanks!
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1005 People Browsing
 102 Signed Up Today
Related Images
  
 964
  
 290
  
 404
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 380