× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
A
6
j
6
c
5
m
5
C
5
d
5
s
5
n
4
i
4
d
4
d
4
J
4
New Topic  
asourdillard asourdillard
wrote...
Posts: 639
Rep: 0 0
6 years ago
If ____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing completion of the project by its required completion time.
 a. total time
  b. free time
  c. total slack
  d. cumulative slack
Read 43 times
1 Reply
Replies
Answer verified by a subject expert
grfrfvfbvrgrfrfvfbvr
wrote...
Top Poster
Posts: 916
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

asourdillard Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

2 hours ago
Correct Slight Smile TY
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  834 People Browsing
 106 Signed Up Today
Related Images
  
 278
  
 202
  
 253
Your Opinion
Who will win the 2024 president election?
Votes: 8
Closes: November 4

Previous poll results: How often do you eat-out per week?